Posted October 21, 2026 | By Eric Engelbert | Updated as the project progresses
The Irvine Company has approval to add 700 apartments to MacArthur Court, its office campus at MacArthur Boulevard and Campus Drive near John Wayne Airport. Two new five-story buildings and about 10,000 sq ft of shops will fill in parking areas, while the existing office towers and garage stay.
It is one of the largest single apartment approvals in Newport Beach this cycle. See all new construction in Newport Beach.
October 2026 Status
| Step | Date |
|---|---|
| Planning Commission recommends approval | October 23, 2025 |
| City Council approves (unanimous) | November 18, 2025 |
| Approval term | Vested for 10 years under the development agreement |
| Construction and leasing | Not yet announced |
Project Details
| Detail | MacArthur Court |
|---|---|
| Location | 4665, 4675, 4680 and 4685 MacArthur Court and 4770 Campus Drive |
| Campus size | About 18.7 acres |
| New homes | 700 market-rate apartments in two five-story buildings |
| Retail | About 10,000 sq ft |
| What stays | Existing office towers and parking structure |
| Affordable housing | 7% of units built off-site (about 49 homes) or an in-lieu fee under the Affordable Housing Implementation Plan |
| Public benefit fee | $3.25 million |
| Environmental review | Covered by the Housing Element program EIR |
| Developer | The Irvine Company |
Email Eric to join the MacArthur Court Apartments Newport Beach update list or call/text 949-430-7500
The Irvine Company in Newport Beach
| Project | Homes | Status |
|---|---|---|
| Villas Fashion Island Phase 2 | 184 apartments | Under construction |
| Block 100, Newport Center | 600 apartments | Approved 2025 |
| MacArthur Court | 700 apartments | Approved November 2025 |
Together that is almost 1,500 new Irvine Company apartments approved or underway in Newport Beach.
The Airport Area Is Becoming a Neighborhood
MacArthur Court is in the Airport Area overlay, the largest of the city's housing zones at 2,577 homes. Within a mile are thousands of approved homes, from rentals to for-sale townhomes:
| Nearby project | Homes | Status |
|---|---|---|
| Redstone Townhomes, Dove Street | 132 for-sale homes | Approved 2026 |
| 1500 Quail Street | 100 for-sale townhomes | Approved April 2026 |
| 1401 Quail Street | 67 for-sale condos | Under construction |
| Uptown Newport and Park Palm | 458 apartments, 30 condos, 23 townhomes | Phase I nearly complete |
| Residences at Airport Village | 444 apartments | Approved April 2024 |
| 1300 and 1400 Bristol | 422 apartments | Approved 2022 and 2024 |
| 4400 Von Karman | 312 apartments | Approved 2021 |
What Measure H Means for This Project
Newport Beach voters decide Measure H on November 3, 2026. It would cut the city's housing capacity from 8,174 homes to 2,900, all for lower and moderate income households. The state housing department (HCD) has said projects that filed applications before a measure like this passes generally keep the rules in place when they filed, so approved projects are expected to proceed either way. Read the full breakdown in our Newport Beach Housing Element post.
Frequently Asked Questions
How many apartments are planned at MacArthur Court?
700 market-rate apartments in two five-story buildings, plus about 10,000 sq ft of retail.
Is MacArthur Court approved?
Yes. The Newport Beach City Council approved it unanimously on November 18, 2025.
Will there be affordable apartments?
The Irvine Company will provide 7% affordable housing off-site, about 49 homes, or pay an in-lieu fee.
When will MacArthur Court open?
No construction or leasing date has been announced.
Get MacArthur Court Updates
I will send leasing and construction news as it happens, plus updates on other new homes in Newport Beach.